CRDA's Key Infrastructure Projects in Amaravati: Timeline and Completion Plans

CRDA's Key Infrastructure Projects in Amaravati: Timeline and Completion Plans

The Capital Region Development Authority (CRDA) has outlined the timelines for several major infrastructure projects in Amaravati. These projects are designed to cater to both residential and official needs, as well as provide essential public services for the city’s growing population.

The following is a list of the key projects, along with their start dates and expected completion times:

Project Start Date Months to Complete
MLA/MLC/AIS Quarters 15th December 2024 6 months
Group-D/Group-B/ Gazetted Officers Quarters 15th December 2024 9 months
NGOs, AIS Quarters & Ministers, Judges Bungalows 15th December 2024 9 months
LPS Infrastructure Zones 1, 2, 3, 4, 5 & 6 15th December 2024 24 months
LPS Infrastructure Zones 7, 8, 9, 10, 11, 12 & 12A 20th December 2024 24 months
Secretariat Towers 1st January 2025 30 months
High Court 1st January 2025 30 months
Assembly 30th January 2025 30 months
Public & Private Sector Land Allottees 15th January 2025 24 months

These projects are part of the ongoing efforts to establish the capital city with adequate facilities for officials, residents, and businesses. The CRDA has set clear timelines for each project, with the majority scheduled to be completed within 6 to 30 months.

As work progresses, these developments will contribute to the city's infrastructure needs, including housing, government buildings, and public amenities.